EWING, NJ – Construction activities remain on pace to complete the Scudder Falls Toll Bridge’s second parallel span and open it to traffic with a phased-in travel shift over two days in mid-August, the Delaware River Joint Toll Bridge Commission announced today.

In the interim, the 24/7 ramp closures will remain in effect on the downstream side of the I-295 EB/Taylorsville Road interchange (Exit 10) in Pennsylvania and the I-295 SB exit ramp to Route 29 SB and NB in New Jersey.  Also, another round of overnight ramp closures are scheduled to be implemented next week at the I-295/Route 29 interchange (Exit 76).

Overall, the project is still on track – with some staging changes – to reach substantial completion by the end of December.

Here are the most immediate changes:

Additional Ramp Closures Next Week at I-295/Route 29 interchange (Exit 76) in New Jersey

  • The current overnight closure of the Route 29 northbound bypass roadway around the interchanges roundabouts and access ramps have been scheduled for three additional weeknights next week – from 8 p.m. to 6 a.m. (next day) Monday, Aug. 2, through Tuesday, 3.  These closures will allow work crews to complete grading, guide rail installations, paving, and erection of an overhead lighting structure along the bypass.  The posted detour on the first two nights will be through the interchange’s roundabouts and northbound connector ramp for travel toward Washington Crossing and Lambertville.
  • The two connector ramps between the roundabouts on the upstream and downstream sides of the interchange are scheduled to be closed for seven weeknights – from 8 p.m. to 6 a.m. (next day) Wednesday, Aug.4, through Friday, Aug. 6, and Monday, Aug. 9, through Thursday, Aug. 12. These closures will allow for the installation of road lighting beneath the road deck of the Scudder Falls (I-295) Toll Bridge’s soon-to-open second span.  Various detours will be utilized for these overnight closures, which also include Route 29 SB traffic be shifted to nearby Route 175/West Upper Ferry Road & Upper River Road.  (CLICK HERE TO VIEW DETOUR MAP PAGE)     

Current Plan to Open Second Bridge

On or about Aug. 16, the contractor will begin a two-day phase in of traffic onto the Scudder Falls Toll Bridge’s parallel downstream span and the reopening of ramps that are currently closed around the clock on the Yardley side of the I-295 EB/Taylorsville Road interchange and the I-295 SB exit ramp to Route 29 on the New Jersey side of the bridge.  These four ramps have been closed and detoured since July 12.  The sequencing of how the ramps will reopen has not yet been determined.

To bring the second bridge online, New Jersey-bound traffic will be moved off the current upstream span to the new span.  This will be achieved by opening the reconstructed and widened I-295 EB approach segment in Pennsylvania along with new approach bridges that will carry I-295 EB across Taylorsville Road and the Delaware Canal.  On the New Jersey side, the reconstructed I-295 SB segment and the two-span approach bridge over the NJ Route 29 NB bypass, the Delaware & Raritan Canal, and Route 175/Upper Ferry Road will open.

The project will then enter its third and final stage of construction.  During this stage, the Scudder Falls Toll Bridge’s upstream span will carry two lanes of Pennsylvania-bound I-295 traffic with an auxiliary lane for accelerating and decelerating traffic at the two adjoining interchanges.  Meanwhile, the bridge’s downstream span will carry two lanes of New Jersey-bound I-295 traffic with an auxiliary lane for accelerating and decelerating traffic at the two adjoining interchanges.  This will allow for completion of the median barriers along I-295 in both New Jersey and Pennsylvania.  After the median barrier and final paving is completed, three lanes will be available along with auxiliary lanes for ramps, on the mainline roadway and the bridge structures.  This is expected to be completed by mid-December

Additional ramp closures and detours will be needed at the I-295/Route 29 interchange to carry out Stage 3 work activities in September and October.  More information on these closures and detours will be announced after the Labor Day weekend.  Additionally, the Route 29 SB bypass lane, which has been closed since March 2020, will reopen in September.

Shared-Use Pedestrian/Bicycle Facility

The bridge’s shared-use pedestrian/bicycle facility and corresponding ramps in New Jersey and Pennsylvania will not open before the Labor Day weekend.  The earliest possible opening would be sometime in the early fall.  (Note:  Under the construction contract, the contractor has until the project’s substantial completion deadline (mid-December) to complete the new facility, which is on the Scudder Falls Toll Bridge’s upstream span.  The facility will connect with the towpaths for the Delaware Canal in Pennsylvania and the Delaware & Raritan Canal in New Jersey.

IMPORTANT NOTE – All dates, travel restrictions, and facility openings identified above are subject to change due to weather, emergencies, traffic, and equipment/materials availability.

Motorists are urged to allow extra time to reach their destinations, reduce speeds and exercise caution when travelling through project work areas.

Share This